Godstone Road, Whyteleafe

Project Inception

SBC competitively tendered this design and build project, and following a post tender negotiation period SBC entered into contract with Tandridge District Council.

Project Journey

Following award of contract SBC completed the design concurrently with clearing pre-commencement planning conditions to enable a swift start of site.

The site is adjacent to a live railway track so to reduce risk to our client SBC obtained Network Asset protection Agreements, enabling SBC and Network Rail to work collaboratively ensuring works by either party had risks manged in partnership and works did not interrupt the progress of either business.

The site sits on a severe slope, so first activities on site were to enable the construction of a 4 meter high retaining wall which  split the site into two levels.  From here construction of the lower block commenced, which was swiftly followed by construction of the upper block.

Works are due to complete in August 2019.

Project Summary:
  • 8 x 2 bed apartments
Partner:
  • Tandride District Council
Expertise:
  • Constrained Sites
  • Homes for Local Authority
  • Sloping Site
  • Adjacent to Rail Tracks
Consultant Partners:
  • MH Architects
  • JMLA Engineers
Completion: August 2019
Contact Us:

230-236 Godstone Road

Whyteleafe

Surrey

CR3 0EF

 

If you like what you see, we’d love to hear from you. We’re always on the lookout for new land and new partnerships.

WORK WITH US
ILM-logo.png
nhbc_logo.png
Accreditations-ISO.jpg
constructionline-logo.png
considerate-constructors.jpg
labc-logo.png
Accreditations-LABC2018.jpg
Accreditation-Considerate-constructions.jpg
Accreditations-Premier-Guarantee-300x80.jpg